Signal | When |
---|---|
A task is On Time if its Projected Finish is before or on its finish date. [ Projected Finish <= Finish date ] | |
Task is not expected to be completed by the deadline based on its % complete so far. [ Projected Finish > Finish date AND Present Date < Finish date ] | |
Task has not been completed by the finish date. [ Task is not 100% complete AND Present date > Finish date ] | |
The task was supposed to start but could not because of its incomplete predecessors. | |
The task has not yet started, and the task date is in Future. | |
Completed | The task is 100% complete. |
...