To add Work Calendar Exceptions for User :

  1. From the main menu, click on Image Removed and then Company Settings.
  2. Under Company section, click on Login with a user with administrator privileges and click on Administration option under the user profile.
  3. Under the Project Management section, click on Work Calendars.
  4. Navigate to the Exceptions tab.
  5. Click Add.
  6. From the For drop-down, select the user for whom you want to enter an exception.
  7. In the Summary box, type the details of your event/exception.
  8. From the Impacts Scheduling drop-down list select an option - Working / Non working.
  9. From the date picker select a date. You can create the event for a whole day or for a specific time (un-check the All Day checkbox).
  10. From the Repeat tab, select an appropriate option.
  11. Click Submit. The exception is added.

 

To add Work Calendar Exceptions for User from RLC :

...

  1. .