  1. Navigate to the project where you want to import those tasks.
  2. From the page actions shown on the right of the project, click on More > Import Tasks (CSV) OR from the Add menu on Gantt, click on Import CSV.
  3. Click Browse and import a file.
  4. Click Next.
  5. Under the Field Mapping, map the fields of your CSV file with the fields provided by Celoxis. You can also map your custom fields from the drop-down.
  6. Under the Number of top rows to skip box, enter the number of rows you want to skip. It is pre-filled with 1 so that the row with column names is skipped.
  7. From the Date Format drop-down list, select a date format.
  8. Click Finish.
     

...