Celoxis provides visual, traffic signal like indicators to inform the task assignees and the project managers of the current status of the tasks. 

Info

These indicators are only shown for projects which are in progress i.e. in Execution stage.

Signal          When

A task is On Time if its Projected Finish is before or on its finish date.

[ Projected Finish <= Finish date ]

Task is not expected to be completed by the deadline based on its % complete so far.

[ Projected Finish > Finish date AND Present Date < Finish date ]
Note: This will only be shown for projects in "Execution" phase. 

Task has not been completed by the finish date.

[ Task is not 100% complete AND Present date > Finish date ]

The task was supposed to start but could not because of its incomplete predecessors.

The task has not yet started, and the task date is in Future. 

The task is 100% complete.

...