The following examples should give you a fair idea as to which scheduling mode works best for your projects & tasks.
 

Manual Scheduling: Manual scheduling is useful when you want to be able to manually enter start and finish dates, without causing those entries to recalculate other aspects of the schedule.

  1. A task that spans 5 days, in which you need only a few hours of effort.

  2. A support activity during particular months of a year.

  3. A date-bound task for which you want to assign multiple resources with different allocations.

  4. Sometimes project schedules are very informal. They begin as simple lists of dates from e-mails

    , meeting

    or meetings with clients.

    Project managers very often

    Managers do not have complete information on these work items.


    For example, they may only be aware how long a task will take, but they do not know it can be started until they have approval. In such cases, the PM might just want to enter the dates agreed with the client. In such cases, manual scheduling of tasks is most efficient way of scheduling projects.


    Sometimes, the PM wants some things done from his/her resources without entering the Allocation or Work as this is irrelevant in this case. For example, on a construction site, the task of getting the materials on-site needs to be done by date X, by resources say Joe and Jack. Work in such cases is not important; so is the allocation. The only important thing is the task deadline that needs to be met. In such cases, the PM or the responsible person needs to enter a Finish date and enter resources. Manual scheduling comes in picture here.

     

 

Automatic Scheduling: Project Managers also need a scheduling engine that automatically calculates dates when entering or changing task information.With automatic scheduling, you let Celoxis build a dynamic schedule that calculates realistic end dates.

  1. In a development project,

    the

    a client discussion to finalize the project details needs to be completed before the SRS can be prepared or the development team can start designing their use cases. The client meeting can be postponed or rescheduled based on availability. This causes the dependent tasks

     to

    to be rescheduled. In such cases, the

    PM

    Manager cannot practically modify the project plan every time. The start date of the dependent tasks should be rescheduled automatically when the predecessor completes. Automatic scheduling takes this into picture and helps the

    PM

    Manager to set dependencies and constraints so that the required tasks

    move or the PM knows about them

    adjust themselves as commitments shift.

  2. For a typical construction project, where contracts, bids and permits are all dynamic in nature and delays are evident, it makes sense to let Celoxis build the project schedule based on the task durations, dependencies and constraints the Project Manager enters.

  3. A specific project task needs a scarce expert resource, and it must be scheduled around the resource's availability. Auto scheduling is your best bet for such tasks.