The Resource Load Chart displays estimated allocations per resource in the selected period. Using this chart, the project manager can drill down further to identify available resources and problematic allocations. You also have the ability to add resource calendar exceptions to set working times, client meetings or holidays that can affect your project schedule.
...
- From the main menu, click on Project.
- Under the Favorite Reports Reports, click on Resource Load Chart.
This is the default report provided by Celoxis.
...
Info |
---|
Green: Resource is optimally allocated. |