SignalWhen
CompletedWhen all the tasks in the project are marked as Complete.
 FutureProject has not yet started and the project start date is in Future.
Info

You can also define your own visual indicators based on your company requirements. To know more, please refer Define your own Visual Indicators section.

Budget Health

Based on the project % complete and the actual cost incurred, the projected cost is derived. This projected cost is then compared with the budget or Cost(Est) if budget is not specified, based on which Celoxis displays the visual (Budget) health indicators.

...