As team members update progress of their tasks, Celoxis auto calculates the projected finish date of the project. The visual health indicators are displayed by comparing the projected finish date with the planned finish dateDeadline.
Signal | When |
---|---|
On Time | Projected Finish Date is less than or equal to project deadline. [ Projected Finish <= Deadline ] |
At Risk | Projected Date exceeds the project deadline. [ Projected Finish > Deadline AND Present date < Deadline ] |
Overdue | Present date has exceeded the project deadline. [ Present date > Deadline AND Project % complete < 100% ] |
...