Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Celoxis provides visual, traffic signal like indicators to inform the task assignees and the project managers of the current status of the tasks.

Signal          When
On TrackOnTrack

A task is On Time if its Projected Finish is before or on its finish date.

[ Actual Projected Finish <= Finish date ]

At Risk

Task is not expected to be completed by the deadline based on its % complete so far.

[ Projected Finish > Finish date AND Present Date < Finish date AND Task is not 100% complete ]]
Note: This will only be shown for projects in "Execution" phase. 

Off Track

Task has not been completed by the finish date.

[ Task is not 100% complete AND Present date > Finish date ]

Blocked

The task was supposed to start but could not because of its incomplete predecessors.

FutureThe task has not yet started, and the task date is in Future. 

...