  1. Does a user have free/available hours in a given time period?
  2. If a task is completed before schedule, will the resources be freed?
  3. If a project is put on hold, will the resources be freed?
  4. Can I locate resources with a specific skill set in a given time period and in a specific department?

The Resource Load Chart (RLC) helps answer the above questions.


Does a user have free/available hours in a given time period?

By default the RLC displays Resource Load Chart (RLC) displays all resources whether assigned or unassigned to tasks. This helps you quickly identify free resources to allocate to incoming work items. You can also use sophisticated filters such as Resource : Workspace or Resource : Search to narrow down on specific resources by workspace or specific keywords.

...