For instance, if project ‘A’ takes 10 days to complete, then after three days’ work, it should be 30% complete but the actual % complete is only 20%. This might be because of reasons like unavailability of resources, or other issues. As a result, the project will run behind the date of completion and it would be at risk. In such a situation, Celoxis displays the signal indicating that the project is At Risk. If a project misses its deadline, then Celoxis displays the signal indicating that the project is Overdue. You can check with the team members of the probable reasons for the delays and take appropriate actions accordingly.

SignalWhen
 CompletedCompletedWhen all the tasks in the project are marked as Complete.
  Future FutureProject has not yet started and the project start date is in Future.

...