Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • You can add a milestone task from the Add option on the Interactive Gantt or by setting the duration of the task as 0d.
  • When you assign resources to this task, the allocation will automatically be pre-filled by 0%.
  •  A milestone has 0 duration and as such has no additional calculation effect on the schedule. 
  • A milestone can be linked to other tasks. 
  • You can set constraint dates on a milestone.
  •  These tasks are not shown on the Resource Load Chart.