 To be able to track a project’s profitability, an accurate estimate of its costs is necessary before tracking the actual costs. You can track the following costs, individually at task level which are rolled up to the summary task level and eventually to the project level.

Labor Cost

A project is executed by its resources and the cost of these resources is represented by Labor Cost. You can specify a per hour cost rate for each resource. For employees or contractors this rate per hour is derived from their salaries. If the resource is say an equipment, the per hour usage rate of the equipment is the labor cost.

...

The estimated labor cost for a task is automatically computed when you assign resources that have an associated User Cost Rate. If multiple resources are assigned to the task, the individual costs of all resources are added to form the total Estimated Labor Cost for the task. 
When the time entered by a resource is approved and marked costable, the actual labor cost of that task is automatically computed. For example, if you take up a project of painting a wall, the labor costs will be the money you pay the resources who are working on this wall.

Material Cost

When a project requires machinery, equipment such as computers, the cost of purchasing or renting this equipment is the Material Cost. Travel or communication costs also add up as material costs. These can be incurred along the life of the project.
Material costs are entered at a task level. The actual Material Cost is computed automatically when an expense marked costable is approved.

...

Code Block
Cost (Act, Non-labor) = Approved Expenses entered by the resource (marked costable)

Fixed Costs

This cost represents the cost that is incurred on the project under all circumstances, independent of any activity or progress of the project. The Accrued Fixed Cost is computed automatically when a task % complete is updated.
For example, if you have hired an office to work on a project, the rent and bills add up as its fixed costs.

...