Based on the task % complete and the actual cost incurred, the projected cost is derived. This projected cost is then compared with the budget or Cost (Est) if Budget is not specified, based on which Celoxis displays the visual (Budget) health indicators.

SignalWhen
Image RemovedImage AddedOn Budget

Projected cost is less than or equal to the budget

[ Projected Cost <= Budget OR Cost (Est) if Budget is not specified]

Image RemovedImage AddedAt Risk

Projected cost has exceeded the budget.

[ Projected Cost > Buget Budget AND Actual Cost < Budget OR Cost (Est) if Budget is not specified ]

Image RemovedImage AddedOver Budget

Actual cost is more than the budget.

[ Actual Cost > Budget OR Cost (Est) if Budget is not specified ]

...