Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

As projects progresses, the project manager might want to get a real-time view of his resources work loads based on actual approved time. This report provides visibility of free resources & helps the PM adjust allocations to ensure optimal resource utilization. 

This report is a dynamic report that displays the Free hours for resources (resource row) and real-time estimated hours based on actual-approved hours and remaining work at the task and project rows. For past dates, the free hours are based on the actual-approved hours, whereas for present & future dates, the remaining work is computed real-time and spread proportional to the resource's availability.

Lets take an example:

A resource Arnold is assigned to a task 'Project KickOff'

...