The custom fields created in MS Project is not imported.

Info

Celoxis can import projects exported from Microsoft Project 2010 and Microsoft Project 2013

To import a project from Microsoft Project:

...

Info
  • When importing, the tasks will be scheduled as per the project/resource calendar defined in Celoxis. So, if there are non-working days in Celoxis calendar, then the tasks dates will be pushed out to the next available date.
  • If you have manually scheduled tasks in the MSP file, then they are imported as-is. For details, refer here.
  • Tasks in MSP which are effort-driven are not supported by Celoxis. The scheduling of such tasks is done as per Celoxis computation.