As team members update the progress of their tasks, Celoxis auto calculates the projected finish date of the project. The visual health indicators are displayed by comparing the projected finish date with the Deadline.
Signal | When |
---|---|
Projected Finish Date is less than or equal to the project deadline. [ Projected Finish <= Deadline ] | |
Projected Date exceeds the project deadline. [ Projected Finish > Deadline AND Present date < Deadline ] | |
Present date has exceeded the project deadline. [ Present date > Deadline AND Project % Complete < 100% ] | |
Project has not yet started, and the project start date is in Future. | |
Not Active | Project is in "Planning" or "Closure" stage. |
...
Based on the project % complete and the actual cost incurred, the projected cost is derived. Thi projected cost is then compared with the budget or Cost(Est) if budget is not specified, based on which Celoxis displays the visual (Budget) health indicators.
Signal | When |
---|---|
Projected cost is less than or equal to the budget [ Projected Cost <= Budget OR Cost (Est) if Budget is not specified] | |
Projected cost has exceeded the budget. [ Projected Cost > Budget AND Actual Cost < Budget OR Cost (Est) if Budget is not specified]] | |
Actual cost is more than the budget. [ Actual Cost > Budget OR Cost (Est) if Budget is not specified] |
...