Columns | Description |
---|---|
Summary | Name of the task. This is a required field. |
Details | Description of the task. This is a required field. |
Start | Start date of the task. |
Finish | Finish date of the task |
Duration | Can be specified in days (d), weeks (w), months (mo) or years(y). For e.g. 2d, 4w, 1y, 2mo |
% Comp | The percentage of task completion |
Budget | The budget of the task. |
Resources | The resources working on the task. Resources can be allocated in hours or %. For e.g Alice[2h] OR Alice[25%] |
WBS | The hierarchy of the task. For e.g. 1, 1.1, 2, 2.1, etc. |
Custom fields | Any additional information regarding the task. These fields need to be first created in Celoxis before you can import the data. For custom fields of type Multi-select dropdown, you can import multiple values by adding | between the values. For e.g: HTML | PHP | CSS |
...