Time phased report is a special report that allows you to view data in a time-phased manner. These report data over a defined time period with a particular zoom level. Zoom can be Day, Week or Month. For complete visibility of your resources, see our resource management section here.  

...

You can create Time - phased reports for the following columns:

Column NameMeaning
Actual CapacityThe actual capacity of the resource(s) as a percentage
Actual EffortApproved Hours
Actual UtilizationThe actual resource utilization i.e Actual Hours / Available Hours as a percentage
Planned CapacityThe estimated capacity of a resource in percentage
Planned EffortThese are the number of hours a resource is allocated or expected to spend on an assigned task.
Planned UtilizationThe planned resource utilization i.e Planned Hours / Available Hours as a percentage
Actual Non-Billable HoursHours approved as non-billable
Available HoursThe working hours of a resource depending on the work calendar timings and exceptions; if any.
EfficiencyThe efficiency or performance of a resource i.e Planned Hours / Actual Hours as a percentage
Free HoursThe remaining planned hours the resource is available.
Free Hours (Realtime)This is
a dynamically computed
an intelligence-built column that shows free hours based on 2 different dimensions depending upon the current time. All data in past is based off the actual (and approved hours
for all past dates and free hours based on remaining effort for
). All data for the present and future dates
till the task's finish date
is based off the remaining effort distributed proportionally. Note that this does not affect any task dates.
Invoiced HoursHours that are marked Invoiced.
Actual Bill HoursHours approved as Billable
Actual CostActual cost of the entity i.e Approved Hours, Expenses, Fixed Cost.
Actual Labor CostApproved Hours of the resource
Actual MarginActual Profit / Actual Revenue
Actual ProfitActual Revenue / Actual Cost
Actual RevenueTime Entries, Expenses approved as Billable
Invoiced RevenueTime Entries, Expenses marked as Invoiced
Planned CostEstimated cost of the entity which includes the Labor cost, Fixed cost, etc.
Planned Labor CostEstimated Cost of the resource depending on the allocation on task * Cost Rate
Planned MarginPlanned Profit - Planned Revenue
Planned ProfitPlanned Revenue / Planned Cost
Planned RevenueResource's planned Hours * Bill Rate
Possible RevenueResource's availability * Bill Rate