Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Info
  • When importing, the tasks will be scheduled as per the project/resource calendar defined in Celoxis. So, if there are non-working days in Celoxis calendar, then the tasks dates will be pushed out to the next available date.
  • If you have manually scheduled tasks in the MSP file, then they are imported as-is. For details, refer here.
  • Tasks in MSP which are effort-driven are not supported by Celoxis. The scheduling of such tasks is done as per Celoxis computation.
  • If you export a project to MS Project and import it back to Celoxis, then the attribute Task Field 10 is mapped to the Celoxis ID field for Task for the seamless import.