To fill time while updating task progress:

  1. Go to your Project.
  2. On the left hand side of the window, click Click Tasks from the list of project specific reports panelview.
  3. Point at a task and click the action drop-down Image Removed Image Added, and then point to Progress and then click Advanced..
  4. In the %* box, type the % Complete.

    Info

    If the % Complete box is grayed out, it means that the task progress can only be updated via the time-entries.

  5. In the Hours box, enter the hours as HH:MM.
  6. Do one of the following:
    • Click the Submit For Approval check box if you want to submit the time entry for approval.
      Or
    • Click Submit. If you clear the Submit For Approval check box, the time entry gets saved for later approval.

...