Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  1. Go to your Project.
  2. Click Tasks from the list of project specific reports view.
  3. Point at a task and click the action drop-down , and then point to Progress and then click Advanced..
  4. In the %* box, type the % Complete.

    Info

    If the % Complete box is grayed out, it means that the task progress can only be updated via the time-entries.

  5. In the Hours box, enter the hours as HH:MM. You can pick appropriate timecode from here. 
  6. Selecting/De-selecting the Send for Approval will Send or Save the time-entry accordingly.
  7. Enter update comments in the text area provided.
  8. Click on Submit.
Info

The details of all the updates can be seen in a Task Update report.