Celoxis provides you with the capability to view the accurate load of your resources, their actual utilization, capacity and efficiency which enables data driven planning and decision making across the project lifecycle. This helps the project manager for better resource planning and management. Using these reports, the manager can move resources across projects or add more free resources on tasks to complete the schedule as expected.
...
These reports contain one or more of the below columns:
Column | Description | Formula | Applicable Toor other Details | ||
---|---|---|---|---|---|
Hours (Est) | These are the number of hours a resource is allocated or expected to spend on an assigned task. If the resource is not allocated, then the Hours(Est) for that task is blank. | Task = T1, Duration = 1d, Resource 1 = 100% and Resource 2 = 50% allocation
| Task, Project, Resource. | This is applicable for Resource, Task, Project. | The information of the resource is then aggregated at task and project level. |
Hours (Act) | These are the approved number of hours a resource has actually spent on a task. The Hours(Actual) for a resource on a task is calculated even if the resource is not allocated on that task and has filled time on it. | Hours (Actual) = Approved hours of a Task. For e.g. Task = T1, Duration = 1d, Resource 1 = 100% Work=8h. Resource fills hours on T1 for 5h which gets approved. Then,
| This is applicable for Task, Project, App items, Non Project, Resource. | The information of the resource is then aggregated at task and project level. | |
Hours (Available) | The working hours of a resource depending on the work calendar timings and exceptions if any. This is applicable for Resource | A work calendar for Monday to Friday with work timings as: 8:00 - 12:00, 13:00 - 17:00 means that a resource assigned to this calendar has Hours (Available)=8 for any particular working day and 40h for a week. If the resource has a non-working exception on say Wednesday, then the Hours (Available) for that week are 32. | Resource. | ||
Free Hours(Est) | These are the remaining estimated hours the resource is available in a particular period. This is applicable for Task, Project, Resource. |
| Task, Project, Resource
| ||
Free Hours (Realtime) | These are remaining actual hours the resource is available in a particular period. This is applicable for Task, Project, Resource. |
| Task,Project, Resource|||
Utilization (Est) | The estimated resource utilization. This is applicable for Resource. | Hours (Est)/Hours (Available) as a percentage | Resource | ||
Utilization (Actual) | The actual resource utilization. This is applicable for Resource. | Hours (Actual)//Hours (Available) as a percentage | Resource | ||
Capacity (Est) | The estimated resource capacity. This is applicable for Resource. | 1- Utilization (Est) as a percentage | Resource|||
Capacity (Actual) | The actual resource capacity. This is applicable for Resource. | 1- Utilization (Actual) as a percentage | Resource | ||
Efficiency | The efficiency or performance of a resource. This is applicable for Resource. | Hours (Est)/Hours (Actual) as a percentage | Resource|||
Hours (Act, Billable) | The actual approved and billable hours. This is applicable for Task, Project, Resource, Apps. |
| Task, Project, Resource, Apps | ||
Hours (Act, Non-Billable) | The actual approved and non-billable hours. This is applicable for Task, Project, Resource, Apps, Non Project. |
| |||
Hours (Invoiced) | The actual invoiced hours. This is applicable for Task, Project, Resource, Apps. |
|
You can also define grouping in the report with the available columns as listed:
...
Info |
---|
The following legends are used to indicate the load: Blue: Underallocated. |