Celoxis provides you with the capability to view the accurate load of your resources, their actual utilization, capacity and efficiency which enables data driven planning and decision making across the project lifecycle. This helps the project manager for better resource planning and management. Using these reports, the manager can move resources across projects or add more free resources on tasks to complete the schedule as expected.
...
Column | Description | Formula | Applicable To |
---|---|---|---|
Hours (Est) | These are the number of hours a resource is allocated or expected to spend on an assigned task. If the resource is not allocated, then the Hours(Est) for that task is blank. | Task = T1, Duration = 1d, Resource 1 = 100% and Resource 2 = 50% allocation
| Task, Project, Resource. |
Hours (Act) | These are the approved number of hours a resource has actually spent on a task. The Hours(Actual) for a resource on a task is calculated even if the resource is not allocated on that task and has filled time on it. | Hours (Actual) = Approved hours of a Task. For e.g. Task = T1, Duration = 1d, Resource 1 = 100% Work=8h. Resource fills hours on T1 for 5h which gets approved. Then,
| Task, Project, App items, Non Project, Resource. |
Hours (Available) | The working hours of a resource depending on the work calendar timings and exceptions if any. | A work calendar for Monday to Friday with work timings as: 8:00 - 12:00, 13:00 - 17:00 means that a resource assigned to this calendar has Hours (Available)=8 for any particular working day and 40h for a week. If the resource has a non-working exception on say Wednesday, then the Hours (Available) for that week are 32. | Resource. |
Free Hours(Est) | These are the remaining estimated remaining hours the resource is available in a particular period. |
| Task, Project, Resource |
Free Hours (Realtime) | These the are remaining actual remaining hours the resource is available in a particular period. |
| Task,Project, Resource |
Utilization (Est) | The estimated utilization of resources based on the estimated allocation and availability. | Hours (Est)/Hours (Available) as a percentage | Resource |
Utilization (Actual) | The actual utilization of resources based on the actual hours and availability. | Hours (Actual)//Hours (Available) as a percentage | Resource |
Capacity (Est) | This is the estimated capacity in percentage that a resource can handle. | 1- Utilization (Est) as a percentage | Resource |
Capacity (Actual) | This is the actual capacity in percentage that a resource handled. | 1- Utilization (Actual) as a percentage | Resource |
Efficiency | This is a efficiency of a resource in percentage depending on the expected and actuals. | Hours (Est)/Hours (Actual) as a percentage | Resource |
Hours (Act, Billable) | These are the actual hours approved as billable for a resource, task, project or project- app items. |
| Task, Project, Resource, Apps |
Hours (Act, Non-Billable) | These are the actual hours approved as non-billable for a resource, task, project or project- app items. |
| Task, Project, Resource, Apps, Non Project |
Hours (Invoiced) | These are the actual hours approved as billable and invoiced for a resource, task, project or project- app items. |
| Task, Project, Resource, Apps |
...
Info |
---|
The following legends are used to indicate the load: Blue: Underallocated. |