This report helps the project manager align the projects in pipeline with the planned & actual resource utilizations to get insight into long-term capacity plans. This helps in informed data-driven decisions to ensure the most efficient use of the resources for ensuring project success.

Image Added

This report shows the Utilization of the resources in the last quarter. Lets take an example of Peter Parker.

Utilization (Est) = Hours (Est)/Hours (Available) as a percentage.
Assume, Peter's Hours(Est) for last quarter is

AprMayJune
361844

Peter works 8 hours a day from Monday to Friday. 

AprMayJune
176176168

So, the