The Resource Load Chart (RLC) also helps you change the resource allocations assignments to quickly resolve problematic allocations. From the same screen, it is possible to add working/non-working exceptions.

To re-allocate resources:

  1. Click the expand icon besides Image Added besides the groupings to expand to the list of tasks the user is assigned to.
  2. For any particular task, click on the Edit link besides the task name.
  3. In the new-pop-up, change the allocation of the resource and click on Ok.
  4. The new allocation of the resource is saved.

...