Code Block | ||
---|---|---|
| ||
<data> <item> <!--create tasks--> <project_id>100</project_id> <summary>Task #1</summary> <detail>This is the task description</detail> <is_manual>true</is_manual> <plan_start>2010-11-02T08:00:00</plan_start> <plan_finish>2010-11-04T17:00:00</plan_finish> <parent_id>12345</parent_id> <predecessors>121121SS,454322FF</predecessors> <priority>2</priority> <assignments>10001[20%],100010[50%]</assignments> <c459099>500</c459099> <!--Formula key of the custom field> </item> <item> <project_id>100</project_id> <is_manual>false</is_manual> <constraint_type>MSO</constraint_type> <constraint_date>2010-11-04T17:00:00</constraint_type>date> <duration>10d</duration> <summary>Task #2</summary> <detail>This is the task description</detail> <assignments>10001[50h]</assignments> </item> </data> |
...