- By simply logging into the application and doing the updates.
Or - By directly replying to the email that they receive from you. In their reply, they enter the new % complete of the task as the “subject” of the email and the updated comments as “body” of the email. You are notified of the update and the reply is automatically filed against the task.
Iframe | ||||||||
---|---|---|---|---|---|---|---|---|
|
To request progress updates on tasks:
- Go to your Project.
- On the left hand side of the window, click Tasks from Open the project specific report - Tasks (List) from the list of project specific reports panel.
- Point to a task and click from the actions drop-down list, and then point to Progress and then Request Progress menu, click on Request an Update. The task owners are notified.
...