When importing the MPP or XML file into Celoxis you can map fields from Microsoft Project to fields in Celoxis.

 

, the following data

Celoxis
Microsoft Project
IDTask Field 10
NameName
Planned StartStart
Deadline
Planned FinishFinish
DurationDuration
Planned EffortWork
Schedule TypeSchedule Type
Constraint Type           
Constraint Type
Constraint DateConstraint Date
Detail
DescriptionDescription
Planned Fixed
Price
CostFixed Cost
PriorityPriority
PredecessorsPredecessors
ResourcesResources 
% Comp% Work Complete
Manually ScheduledTask Mode