When importing the MPP or XML file into Celoxis you can map fields from Microsoft Project to fields in Celoxis.
, the following data
Celoxis | Microsoft Project |
---|---|
ID | Task Field 10 |
Name | Name |
Planned Start | Start |
Planned Finish | Finish |
Duration | Duration |
Planned Effort | Work |
Schedule Type | Schedule Type |
Constraint Type | Constraint Type |
Constraint Date | Constraint Date |
Description | Description |
Planned Fixed |
Cost | Fixed Cost |
Priority | Priority |
Predecessors | Predecessors |
Resources | Resources |
% Comp | % Work Complete |
Manually Scheduled | Task Mode |