Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

The Resource Load Chart displays estimated allocations per resource in the selected period. Using this chart, the project manager can drill down further to identify available resources and problematic allocations. You also have the ability to add resource calendar exceptions to set working times, client meetings or holidays that can affect your project schedule.

...

So, the allocation for Peter (Planned Hours (Est)) will be divided across the planned dates for the task (32h / 4d) which is as follows:

1st2nd3rd4th
8888

As the resource is optimally allocated, the legend for the resource shows up in green for that assignment.

...

  1. From the main menu, click on Project.
  2. Under the Image Removed Reports, click on Resource Load Chart.
    This is the default report provided by Celoxis.

...

  1. View.
  2. The report will be listed here as a favorite report by default.
Info

Green:  Resource is optimally allocated.
Blue:  Resource is under allocated.
Red:  Resource is over allocated.
Gray: Exceptions.
Yellow (NW) : Non-Working.

...