Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

As projects progressesprogress, the project manager might want to get a real-time view of his resources' work loads based on actual approved time. This report provides visibility of free resources & helps the PM adjust allocations to ensure optimal resource utilization. 

Image Removed

 

This report is a dynamic report that displays the Free hours for resources (resource row) and real-time estimated hours based on actual-approved hours and remaining work at the task and project rows. For past dates, the free hours are based on the actual-approved hours, whereas for present & future dates, the remaining work is computed real-time and spread proportional to the resource's availability.

Image Added

Lets take an example:

A resource Peter Parker Arnold is assigned to a task 'Setup CubiclesProject KickOff'

  • Task Schedule: From 10th 11th to 17th 13th in a month i.e 6 3 days
  • Allocation: 50%
  • Work: 12h (Work)
  • Allocation: 25%

So, the allocation for Peter (Hours (Est)) Arnold the Planned Hours will be divided across the planned dates for the task (12h / 6daccording to availability and allocation (50%) which is as follows:

10th
11th
12th
15th
13th
16th
4
17th
4
222222

...

4

Arnold fills time-entry for of 4 hours on 10th and is approved. So, on 10th (past date), the real-time assignment for Peter on 10 is 4h. Now, the remaining work is 8h which is divided across the available duration of the task i.e. 8/4=2h from 12th of the month; excluding todayfor 11th. Today is 12th, 12 PM. This is reflected on 11th (past) for that task row. The remaining effort for the task is now (12 - 4) = 8 hours, which will be spread over today and future duration of the task proportional to Arnold's availability.

As 4 hours of Arnold's working time today has already elapsed (regular working times: 8 AM-5 PM), the remaining available hours for today is 4 and for next day is 8. So, Arnold's remaining availability is  12 h to complete the 8 h of remaining work over the remaining duration of the task. 
Today(at 12:00 PM), Arnold will have to do 2.7 h of work, i.e For 8 hours of remaining work, Arnold is available for 12 hours. So, how much work should he do for 4 hours of availability? (8*4)/12=2.7

And remaining 5.3h (8-2.7) is for 13th.

So, for Arnold, remaining availability (free hours) for the dates is as follows:

11th (past)
12th (present)
13th (future)
4 (8-4 approved hours)2.7 (8-5.3)5.3 (8-2.7)

 

 

Info

If a task is completed before schedule (i.e. %Complete = 100%) then the remaining work (if any) will not be spread over the future duration of the task.