- Go to the Gantt of your project.
- Select a task and click on the Copy icon or (s) and press Ctrl+C on the keyboard OR right-click on the task and select Copy.
- Now, select the task under which you want to paste the task . You can do this my clicking on the paste icon or and press Ctrl+V on the keyboard OR right-click on the task and select Paste. The new task(s) is now seen under the task.
To Move a task to another project :
- Go to the Gantt of your project.
- Select Right-click on the task you want to copy to another project.
- From the Gantt menu bar, click on More.
- Click wish to move and click on Move.
- On Now, in the new pop-up window, select the appropriate option to select pick the project where the task will be moved and click on Next.
...
- . The task will move to the selected project.
Moving the task will move the costs, documents, updates made on the task to the new selected project.