Time phased report is a special report that allows you to view data in a time-phased manner. These report data over a defined time period with a particular zoom level. Zoom can be Day, Week or Month. For complete visibility of your resources, see our resource management section here.  

To create a Time Phased report:

  1. On From the main menu, click Reports > All Reports.
  2. From the New report...drop-down list, select Time Phased.
  3. In the Name* box, type the name of the report.
  4. In the Description box, type the description.
  5. From the Share with usersthe Visible to Users drop-down list, select the appropriate option with whom you want to share the report.
  6. From the Share with clientsVisible to Clients drop-down list, select the clients with whom you want to share the report.
  7. In the Filters section, from the Add filter... drop-down list, select a filter. The selected filters are displayed under the Filter column.
  8. Select the Prompt? check box if you wan to display the selected filters in the report output window.
  9. In the View section, under Tabular, select the columns and options of your choice.
    1. Choose 'Show totals only' if you want to show see totals at each level of grouping without bothering about the individual details.
    2. Choose 'Cumulative' if you to  to see increasing quantities by successive additions.
  10. Click Save to save the report. The created report will be displayed.

...

  1. .

Image Added

You can create Time - phased reports for the following columns:

Column NameMeaning
Actual CapacityThe actual capacity of the resource(s) as a percentage
Actual EffortApproved Hours
Actual UtilizationThe actual resource utilization i.e Actual Hours / Available Hours as a percentage
Planned CapacityThe estimated capacity of a resource in percentage
Planned EffortThese are the number of hours a resource is allocated or expected to spend on an assigned task.
Planned UtilizationThe planned resource utilization i.e Planned Hours / Available Hours as a percentage
Actual Non-Billable HoursHours approved as non-billable
Available HoursThe working hours of a resource depending on the work calendar timings and exceptions; if any.
EfficiencyThe efficiency or performance of a resource i.e Planned Hours / Actual Hours as a percentage
Free HoursThe remaining planned hours the resource is available.
Free Hours (Realtime)This is an intelligence-built column that shows free hours based on 2 different dimensions depending upon the current time. All data in past is based off the actual (and approved hours). All data for the present and future dates is based off the remaining effort distributed proportionally. Note that this does not affect any task dates.
Invoiced HoursHours that are marked Invoiced.
Actual Bill HoursHours approved as Billable
Actual CostActual cost of the entity i.e Approved Hours, Expenses, Fixed Cost.
Actual Labor CostApproved Hours of the resource
Actual MarginActual Profit / Actual Revenue
Actual ProfitActual Revenue / Actual Cost
Actual RevenueTime Entries, Expenses approved as Billable
Invoiced RevenueTime Entries, Expenses marked as Invoiced
Planned CostEstimated cost of the entity which includes the Labor cost, Fixed cost, etc.
Planned Labor CostEstimated Cost of the resource depending on the allocation on task * Cost Rate
Planned MarginPlanned Profit - Planned Revenue
Planned ProfitPlanned Revenue / Planned Cost
Planned RevenueResource's planned Hours * Bill Rate
Possible RevenueResource's availability * Bill Rate