Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

As projects progressesprogress, the project manager might want to get a real-time view of his resources' work loads based on actual approved time. This report provides visibility of free resources & helps the PM adjust allocations to ensure optimal resource utilization. 

...

So, the allocation for Arnold (Hours (Est)) the Planned Hours will be divided across the planned dates for the task according to availability and allocation (50%) which is as follows:

11th
12th
13th
444

Arnold fills time-entry of 4 hours for 11th. Today is 12th, 12 PM. This is reflected on 11th (past) for that task row. The remaining effort for the task is now (12 - 4) = 8 hours, which will be spread over today and future duration of the task proportional to Arnold's availability.

...

So, for Arnold, remaining availability (free hours) for the dates is as follows:

11th (past)
12th (present)
13th (future)
4 (8-4 approved hours)2.7 (8-5.3)5.3 (8-2.7)
2.7 (8-5.3)

 

 

Info

If a task is completed before schedule (i.e. %Complete = 100%) then the remaining work (if any) will not be spread over the future duration of the task.