As projects progresses, the project manager might want to get a real-time view of his resources work loads based on actual approved time. This report provides visibility of free resources & helps the PM adjust allocations to ensure optimal resource utilization.
Lets take an example:
A resource Arnold is assigned to a task 'Project KickOff'
- Task Schedule: From 11th to 13th in a month i.e 3 days
- Work: 19h (Work)
- Allocation: 50%
So, the allocation for Arnold (Hours (Est)) will be divided across the planned dates for the task according to availability and allocation (50%) which is as follows:
11th | 12th | 13th |
---|---|---|
4 | 4 | 4 |
Arnold fills time-entry of 4 hours for 11th. Today is 12th 12:00 PM.
As 4 hours of Arnold's working time as already passed (8AM-5PM), the remaining available hours for today is 4 and for next day is 8. So, Arnold is available 12h to complete the 8h of remaining work for the planned dates of the task.
So, today(12th 12:00 PM), Arnold will have to do 2.7h of work in 4h
i.e For 8 hours of remaining work, Arnold is available for 12 hours. So, how much work should he do for 4 hours of availability? (8*4)/12=2.7
And remaining 5.3h (8-2.7)on 13th for this task.
So, for Arnold, remaining availability for the dates is as follows:
11th | 12th | 13th |
---|---|---|
4 (8-4 approved hours) | 5.3 (8-2.7) | 2.7 (8-5.3) |