Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 4 Next »

The Resource Load Chart displays estimated allocations per resource in the selected period. Using this chart, the project manager can drill down further to identify available resources and problematic allocations. You also have the ability to add resource calendar exceptions to set working times, client meetings or holidays that can affect your project schedule.

Let's look at an example highlighted in the screenshot above: 
A resource Peter Parker is assigned to a task 'Survey commercial spaces'

  • Task Schedule: From 1st to 4th in a month i.e 4 days
  • Work: 32 h (Work)
  • Allocation: 100%

So, the allocation for Peter (Hours (Est)) will be divided across the planned dates for the task (32h / 4d) which is as follows:

1st2nd3rd4th
8888

 

 

 

  • No labels