When doing a MSP Import:
- MS Project files maintains dates even for a manually scheduled tasks. These dates are silently computed by MSP to indicate the dates as if the tasks are auto-scheduled.The MPP/XML file has these dates and are used Celoxis. These tasks will be imported as manually scheduled tasks in Celoxis.
When doing a MSP Export:
- Celoxis' manually scheduled tasks will be exported as manually scheduled tasks into MSP.
- Summary tasks will be exported as auto-scheduled tasks.