Exporting your Celoxis project to MS Project is helpful if you need to work on your project plan when you are disconnected from the internet while travelling or if working in Microsoft Project is more convenient for you. In such a scenario, you can export your project to Microsoft Project, make changes and re-import it. Exporting to Microsoft Project may also be useful to share your project plan with clients, stakeholders or others that have Microsoft Project but do not have access to Celoxis.

To export a project to Microsoft Project:

  1. Go to the project.
  2. Under the More actions on the Interactive Gantt or from the project's actions drop-down , point to Export.
  3. Click on Microsoft Project.
  4. The .xml file is saved to your disk.

To import the XML file into Microsoft Project:

  1. Start the Microsoft Project.
  2. Click File, and then click Open.
  3. Select the XML file saved from Celoxis.
  4. Choose As a new project when prompted on how to open it.

  • When tasks are exported to Microsoft project, allocation in hours is converted into % (percent).
  • When exporting a project with baseline from Celoxis, it is imported as Baseline in MS Project.