If you need to change the task attributes, you edit a task.

  1. Go to the Interactive Gantt view for your project.
  2. Right click on a task and select Edit OR Select a task and click on the edit icon (pencil-shaped).
  3. The information is divided into 4 tabs : Basic, Advanced, Custom Fields, Details.
    1. The Basic tab shows attributes like : Name, Start Date, Finish Date, Duration, Work, % Complete, Schedule Type, Predecessor, Resources.
    2. The Advanced tab shows attributes like : Constraint Type, Constraint Date, Priority, State, Start(Actual), Finish(Actual). The 'Allow Time Sheets?' checkbox, which when checked allows you to fill time on tasks. It also lets you update the financial columns like : Budget, Cost (Est, Material), Cost (Fixed). 
    3. The Custom Fields tab displays all the custom fields attached to a task. You can view/edit values from this tab; per task.
    4. The Details tab allows you to enter/edit the description text for a task. 

For information on tasks attributes, click here

Certain attributes for summary tasks cannot be edited (start/end dates, duration, schedule type, effort, constraints and financials)