The RLC also helps you change the allocation of a resource so that you can plan your resource utilization in a more realistic manner. From the same screen, it is possible to add working/non-working exceptions.
To re-allocate resources:
- Click the small triangle sign besides the user's name to expand the list of projects and tasks user is assigned to.
- For any particular task, click on the Edit link besides the task name.
- In the new-pop-up, change the allocation of the resource and click on Ok.
- The new allocation of the resource is saved.
To enter working / non-working time:
- For any particular date, click on the resource name where you want to add an exception.
- Select the appropriate option from the list.
- An exception is added for the selected option.