In Celoxis, there are two ways by which you can add task dependencies within the same project.

     1. By manually entering the ID of the predecessor task:

     2. By dragging dependencies from Gantt Chart view: 

  • You can enter multiple dependency on a task by separating them by a comma (,). For example 3FF,4SS as seen in the example above.
  • The lead/lag time can be set in hours,days, weeks, months, years. For example - 34[-10d] or 3[2w] or 45[5h] or 56[-3w] or 123[4mo] or 23[-1y]