Fields/Columns exported

Fields/Columns exported

Following information is exported:

  • Task attributes
  • Parent-child relationships
  • Dependencies including lead/lag time
  • Constraints
  • Predecessors
  • Resource allocations
  • Resource list - eases project managers job while assigning resources to tasks
  • Resource vacations
  • Resource Working calendar
  • Company working hours
  • Company holidays
  • Baseline
  • 1 person day
  • Hours per week/month
     

Whenever you make changes in Celoxis, you need to export it back so that MS Project has you latest changes.

Related content

Fields/Columns exported
Fields/Columns exported
More like this
Fields/Columns exported
Fields/Columns exported
More like this
Exporting Project to Microsoft Project
Exporting Project to Microsoft Project
More like this
Exporting Project to Microsoft Project
Exporting Project to Microsoft Project
More like this
Exporting Project to Microsoft Project
Exporting Project to Microsoft Project
More like this
Exporting Tasks
Exporting Tasks
More like this