Baseline
Before you start executing your project, you may want to set a snapshot in time so that you can compare it with your updated schedule. As your project progresses, this reference point helps you track what was originally planned and what changed on the project.Â
Celoxis allows you to create a single baseline for your project of schedules, tasks and cost information in your project plan at that point of time. You can create baseline on two options
- Baseline for all tasks in the project.
- Baseline for the selected tasks in the project.
To Set a baseline :
- Navigate to your project.
- Go to the Interactive Gantt chart for your project.
- Click on Baseline.
- Click on Set. Select the appropriate option.
Clicking on  Project, baselines all the tasks in your project. If you need to baseline specific tasks, select them before you click on Selected Tasks. - An appropriate message is shown to confirm your clicks. Saving this will baseline your project or selected tasks in the project.
Only a user who is the Project Manager or has Edit Project privilege can set or clear a baseline for project or tasks.
To View a baseline :
- Navigate to your project.
- Go to the Interactive Gantt chart for your project.
- Click on Baseline.
- Select the View check-box. The baseline task(s) bars are shown on the Gantt chart.
To Clear a baseline :
Navigate to your project.
Go to the Interactive Gantt chart for your project.
Click on Baseline.
- Point to Clear an select the appropriate options to clear the baseline for your Project or Selected tasks.
- A message is shown to confirm this. Click on Clear.
Â
To view the baselined values, you need to create a project/task report with the baseline columns.