Project Baseline Attributes

Attribute
Description
R/RW
%Complete (Planned, Baseline)This indicates the % Complete (Planned) of the project when it was baselined. This is compared against the Deadline (Baseline) date of the project.
So, even if your Deadline date changes, the % Complete (Planned, Baseline) will always be calculated with respect to your Deadline (Baseline).
R
Budget (Baseline)The budget of the project when the project was baselined.R
Cost (Est, Baseline)The estimated cost of the project when the project was baselined.R
Deadline (Baseline)The Finish/Deadline date of a project when it was baselined.R
Deadline Variance (Baseline)The difference in days between the current Deadline date and the Deadline date when the project was baselined.R
Start (Baseline)The start date of the project when it was baselined.R
Start Variance (Baseline)The difference in days between the current Start date and the Start date when the project was baselined.R
Work (Baseline)The Work in hours when the project was baselinedR
Work Variance (Baseline)The difference between the current Work and the Work when the project was baselined.R