Project Baseline Attributes
Attribute | Description | R/RW |
---|---|---|
%Complete (Planned, Baseline) | This indicates the % Complete (Planned) of the project when it was baselined. This is compared against the Deadline (Baseline) date of the project. So, even if your Deadline date changes, the % Complete (Planned, Baseline) will always be calculated with respect to your Deadline (Baseline). | R |
Budget (Baseline) | The budget of the project when the project was baselined. | R |
Cost (Est, Baseline) | The estimated cost of the project when the project was baselined. | R |
Deadline (Baseline) | The Finish/Deadline date of a project when it was baselined. | R |
Deadline Variance (Baseline) | The difference in days between the current Deadline date and the Deadline date when the project was baselined. | R |
Start (Baseline) | The start date of the project when it was baselined. | R |
Start Variance (Baseline) | The difference in days between the current Start date and the Start date when the project was baselined. | R |
Work (Baseline) | The Work in hours when the project was baselined | R |
Work Variance (Baseline) | The difference between the current Work and the Work when the project was baselined. | R |