- Changing auto scheduled task to manually scheduled:
- Existing constraints (Type and Date) are retained but will not be honored.
- Dependencies will remain as is but will not be honored.
- Constraints will reset to ASAP.
- Certain fields like Duration, Constraint Type, Constraint Date, Predecessor will not be visible on the Edit pop-up screen of the task.
- Changing manually scheduled task to auto scheduled:
- Task will get rescheduled as per auto logic.
- Certain fields like Duration, Constraint Type, Constraint Date, Predecessor will be visible on the Edit pop-up screen of the task.
- If the Constraint type of the manually scheduled task was set, it will be reverted back to ASAP.
- Constraints and dependencies will be honored once set after the change.