Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 3 Next »

Copying or moving the task copies the duration, schedule type, work, resource allocation, budget, estimated costs, documents, Security (object level) etc. You can set a different start date for the clone and the finish date will be computed. 

To clone a task to a different project, you can first copy the task, and then move it across the projects. This also copies the same task attributes mentioned above.

To copy a task in a project :

  1. Go to the Gantt of your project.
  2. Select a task and click on the Copy icon or press Ctrl+C on the keyboard.
  3. Now, select the task under which you want to paste the task. You can do this my clicking on the paste icon or Ctrl+V on the keyboard The new task is now seen under the task. 

     

To Move a task to another project :

  1. Go to the Gantt of your project.
  2. Select the task you want to copy to another project.
  3. From the Gantt menu bar, click on More.
  4. Click on Move.
  5. On the pop-up window, select the appropriate option to select the project and click on Next.


     

 

 

  • No labels