Projects rarely proceed as per plan. Real world situations may change a project’s schedule, and the projects may even get delayed. Celoxis provides visual, traffic signal like indicators to indicate schedule and cost health of a project. A quick glance at the visual health indicators can alert a manager to take corrective action before a setback occurs. 

...

As team members update the progress of their tasks, Celoxis auto calculates the projected finish date of the project. The visual health indicators are displayed by comparing the projected finish date with the Deadline Finish (Est)

SignalWhen
Image Modified

Projected Finish Date is less than or equal to the

project deadline

Project's planned Finish i.e Finish (Est).

[ Projected Finish <=

Deadline

Finish (Est) ]

Image Modified

Projected Date exceeds the

project deadline

Finish (Est).

[ Projected Finish >

Deadline

Finish (Est) AND Present date <

Deadline

Finish (Est) ]

Image Modified

Present date has exceeded the project

deadline

Finish (Est).

[ Present date >

Deadline

Finish (Est) AND Project % Complete < 100% ]

Image Modified
Project has not yet started, and the project start date is in Future.
Image Modified
Project is in "Planning" or "Closure" stage.

For instance, if project ‘A’ takes ten days to complete, then after three days’ work, it should be 30% complete, but the actual % complete is only 20%. The reason might be because of reasons like unavailability of resources, or other issues. As a result, the project will be delayed from the date of completion, and it would be at risk. In such a situation, Celoxis displays the signal indicating that the project is At Risk. If a project misses its deadlineitsdeadline, then Celoxis shows the signal stating that the project is Overdue. You can check with the team members of the probable reasons for the delays and take appropriate actions accordingly.

 


Info

You can also define your own visual indicators based on your company requirements. To know more, please refer Define your own Visual Indicators section.

...

Based on the project % complete and the actual cost incurred, the projected cost is derived. Thi projected cost is then compared with the budget or Cost(Est) if budget is not specified, based on which Celoxis displays the visual (Budget) health indicators.

SignalWhen
Image Modified

Projected cost is less than or equal to the budget

[ Projected Cost <= Budget OR Cost (Est) if Budget is not specified]

Image Modified

Projected cost has exceeded the budget.

[ Projected Cost > Budget AND Actual Cost < Budget OR Cost (Est) if Budget is not specified]]

Image Modified

Actual cost is more than the budget.

[ Actual Cost > Budget OR Cost (Est) if Budget is not specified]

For instance, your budget for a project is $1000. Now, when you spend $1000 on the project, ideally your project should have been 100% completed or when you have spent $500, your project should be 50% completed, and then in this situation, Celoxis displays the signal indicating that your project is "On Budget". But if you have spent $600, and your project is only 50% completed, that means by the time your project is 100% complete, you would have spent $1200 at the current rate of spending. In such a situation, Celoxis displays the signal indicating that your project is At Risk. However, if your project is only 80% completed, and you have already spent $1000, then, in such a situation, Celoxis displays the signal indicating that the project is "Over Budget." You can check with your team members of the probable reasons for the delays and take appropriate actions accordingly. 


Note

These schedule signals are not calculated regularly as these are very intensive operations which might slow down the application. Hence, you need to recalculate the projections so that the health indicators, projected dates show up correctly. On how to recalculate the projections, please click here.