Recalculating Projections

As a project progresses, tasks often tend to get delayed. It is very useful for a Manager to be able to compute the finish date based on current progress. Celoxis allows you to compute a projected finish date for your tasks and project. This can be done by clicking on Recalculate Projections for a project.

The attributes which are calculated are:

  • Projected Start date of tasks.
  • Projected Finish date of a tasks.
  • Projected Finish date of a project.
  • RAG (schedule and budget) status of project.

To recalculate projections for a single project:

  1. Go to your Project and then click on More followed by Recalculate Projections. 


To recalculate projections for a multiple projects:

  1. Run a project report or view where you will see the projects for which you wish to calculate the projections.
  2. Select those projects and from the bulk action menu (3-line menu), click on Recalculate Projections.Â