For instance, your budget for a task is $200 (this includes labor, material and fixed cost if any). Now, when you spend $200 on the task, ideally your task should have been 100% completed. If your task is 50% complete and you have spent $100, Celoxis displays the green signal indicating that your project is "On Budget".
But if you have spent $150, and your project is only 50% completed, that means by the time your project is 100% complete, you would have spent $300 by the current rate of spending. In such a situation, Celoxis displays the signal indicating that your task budget is At Risk. And if your actual cost spent exceeds $200 Celoxis displays the signal indicating your task is Over Budget. 

Note

These schedule signals are not calculated regularly as these are very intense operations which might slow down the application. Hence, you should recalculate the status to see this correctly. To recalculate the status, please click here.