When doing a MSP Import:
- MS Project files maintains dates even for a manually scheduled tasks. These dates are silently computed by MSP to indicate the dates as if the tasks are auto-scheduled.The MPP/XML file has these dates and are used Celoxis. The Schedule type of such tasks will be ‘Fixed Dates’.
When doing a MSP Export:
- Fixed dates scheduled tasks will be exported as manually scheduled tasks.
- Summary tasks will be exported as auto-scheduled tasks.
...